Why is
your favorite game late? Why is your own project slipping? Chances are
good that one of the reasons is an acute case of feature creep. Feature
creep -- requirements changing during development -- is a major risk
for virtually every game project. Various project size changes lead
to increased complexity, effort, schedule, and budget. Given the average
complexity of a game project, it's safe to say that almost all of us
have experienced feature creep. If uncontrolled, changing requirements
can overwhelm even the best-planned effort, and quickly put your project
in trouble.
Case
Study: Too Eager to Please
You are
probably involved with managing projects because you are good with people.
You probably like to make people happy. That same attribute that serves
you well, however, can also get you into big trouble. Take, for example,
one of my first projects.
My company
was hired to build a creativity-based kids' product for a major toy
corporation. Eager to please a new client, we committed to a fairly
short schedule and an aggressive list of features. The design wasn't
finalized before we started development, and I didn't resist any feature
requests. I didn't want the client to think we couldn't deliver what
they wanted. After all, none of the individual requests was anything
very complicated. More image processing effects, fancy scene transitions,
a rollover help system -- anything they wanted, we could do without
a problem. Until, that is, the engineers on the team started to raise
concerns that they were running out of time to get everything implemented.
In my
initial scheduling, I hadn't planned on anything that wasn't in the
original specification. I had failed to realize that the original specification
was filled with design holes that would require filling with new dialog
boxes, help messages, error messages, and other completely necessary
features. Each day seemed to add "just a small request," until
we realized we would be late for our first major milestone. In an effort
to get the project back on track, I tried to work with the client to
cut features from the product. This only managed to upset the client,
without achieving enough significant cuts to get the project back on
track. Ultimately, we shipped the project several weeks late to a client
that was less than completely satisfied.
Wanting
to avoid my pain, you may be tempted to simply freeze your design and
ban feature requests from your project. But when it comes to changing
requirements, abstinence is not the answer. In a rapidly changing industry,
designs must evolve during development for a product to stay on the
cutting edge. When you get feedback from early users such as beta testers,
you need to pay attention to the valuable input you are getting. Your
goal is to balance flexibility with sound project management. It's not
easy, but it can be done.
Case
Study: Do You Want to Bet One Month's Salary?
After
the failure described above, I was determined to do a better job of
preventing feature creep. I was convinced I could do it without being
completely inflexible and upsetting the client. At the beginning of
the project, however, it looked like my goal would be tough to achieve.
The client was asking for a lot of features, and on a very short schedule.
After
my previous experience, one thing was clear to me: it's better to have
the tough discussions about features at the beginning of the project
instead of toward the end of the project. Convinced by a colleague that
it was better to do no business than bad business, I risked upsetting
the client by raising the feature and schedule mismatch in our first
meeting. I realized that the client would not simply want to hear me
whine, but would want a solution. Even better would be to offer the
client multiple alternative solutions. Armed with a feature list, a
short schedule, and a good technical lead that could estimate accurately,
I did a preliminary schedule.
At this
early stage, most estimates were rough, and covered a range from a low
estimate to a high estimate. I understood the product design and it
seemed solid, but knew that unexpected issues would come up during development,
so I added some extra room to the schedule for an unknown task. I then
created three feature lists. We could build the product with all of
the features in the long list if we used all the low estimates. Trimming
a few features, we could build the medium list if we used an average
of the low and high estimates. Trimming a few more features, we could
build the short list if we used all the high estimates.
I presented
the three feature lists to the client, and tried to explain the different
levels of risk in terms they could understand. "If we build the
shortest list of features, I am confident we will be on schedule. I'm
so confident, that I would bet one month of my salary that we deliver
on schedule. In the medium list of features, I would still take that
bet, but only if I got 2 to 1 odds. And I wouldn't bet at any odds that
we could build the long list of features on schedule." The client
opted for the middle set of features, which is what I expected.
In the
early meetings to work out design details, I kept an eye on the list
of features to make sure it wasn't growing too large. But I also suggested
features that I thought would be helpful to the product without adding
a lot of work. I knew that I had a little bit of room in the schedule,
and I wanted to use that room to build the best product I could for
the client. This helped earn the trust of the client. We both felt that
we had the same goal: build the best product we can within the required
short schedule.
During
development, the client requested many minor changes. A few of them
I agreed to, since I knew that they really didn't have a big effect
on the development effort, and would help the product. But most of the
changes I resisted. If I could find an alternative solution, I would
present that to the client. They almost always accepted the alternative
happily. If I couldn't find an alternative and knew the change would
add risk to the project, I simply explained that fact. Given the short
schedule and everyone's desire to ship on time, the client understood
why I was resisting changes. Since I had offered some features during
design and agreed to some changes, the client understood that I had
the product's interest at heart.
This project
was completed on time and on budget. While not every conversation with
the client was easy, in the end we all still respected each other and
liked working together. I had learned an important lesson: I had controlled
feature creep and also managed to keep the client happy.
|